Got the the factory 7:00 AM in the morning, and the workers there had already moved the machine to where the center line was. We then asked them to move the machine to the center point, but before machine got to the center point we could see that the machine was already interfering the RGV system.

We double checked our measurements, however, everything was correct according to the machine layout blueprint. If our measurements were correct, then it must be something wrong with the blueprint. Shortly, we made a phone call back to the office, after some time we were told that the blueprints we had were for pre-minor changed machines, not for the minor changed machines. No wonder it did not look right when we tried to set the machine down.

Both of my coworker and I felt frustrated although it was not our fault to begin with. Nonetheless, we felt that customers must think we are dumb couldn't even read the blueprint correctly. As the results, we had to move the machine out of the way for the workers to re-drill the holes that were based on the REAL center lines.

Finally, we moved the machine to the real center point this time, and we began to house cleaning of the machine to get rid of the grease. We also took off the brackets off the machines. The rest of the stuff would require power to do, and that would be for tomorrow.

No comments:

Post a Comment